An office is ready when people can do their essential work. Having desks delivered is only one part of that. Work backwards from the first process you need: who must be reachable, which systems must run and who can authorise the start?

1. Define the minimum operation you need
Make the goal specific: which work must be possible again, and by when? A general promise of no downtime cannot replace this plan.
Start with the activities whose failure would immediately affect customers, deadlines or payments: answering calls, handling orders or accessing a business application, for example. For each activity, list the people, equipment, connections and records it needs. Use this to determine which workstations must be available first.
Management should decide how long each activity may be interrupted and which temporary arrangement is acceptable. A single moving weekend will not suit every business. Deliveries, external providers and the people who can answer questions also need to fit that window.
The BSI's business continuity resources address fallback options and dependencies. This guide applies that planning idea to an office move through an original editorial checklist; it is not a complete business continuity programme.
- Record an owner, latest acceptable restart and required resources for each activity.
- Describe minimum operation: which tasks and how many workstations are needed first?
- Prepare an approved fallback with a reachable contact in case the new site is not yet usable.
2. Name the people responsible for tasks and approvals
Appoint an internal move lead and a deputy. Give every task one person responsible for confirming completion, even when several people contribute. Put names and callback numbers in an appropriately protected working document available to the people who need it.
A transport booking does not automatically include setting up IT, telephony or electrical installations. Agree each handover with the relevant provider: what is being handed over, to whom and in what condition?
| Task | Internal responsibility to assign | Evidence before the next step |
|---|---|---|
| Minimum operation and restart decision | Management or an authorised move lead | Recorded criteria and decision |
| Workflows and team allocation | Owners of the affected departments | Confirmed priorities and staffing |
| Keys, rooms and building access | Facilities contact coordinating with the landlord | Confirmed access, loading times and rooms |
| IT, data and communications | Named internal IT team or appointed IT provider | Confirmed backup, cutover and test plan |
| Furniture, cartons and transport | Named moving partner within the agreed scope | Agreed inventory, destination zones and service boundaries |
| Restart updates and fault reporting | Named internal contact and deputy | One reporting channel and an up-to-date contact plan |
3. Assign destination zones before packing
Use an agreed room plan with clear destination references, such as room A, workstation A-04 and the relevant inventory ID. The list, carton and destination room must use matching references. Colour coding can help, but should not be the only way to identify a destination.
Separate delivery, temporary storage, assembly and areas released for work. An empty corridor is not a storage zone. Escape routes and emergency exits must remain clear; the person responsible at the business should check the actual layout against applicable requirements.
- Assign the furniture and equipment for each workstation, including items that will initially stay in storage.
- Keep screws, brackets and accessories in closed containers with the matching inventory ID.
- Move confidential records in closed containers with neutral IDs; keep the contents list separate with restricted access.
- Agree where damaged or unidentified items can await a decision without obstructing circulation routes.
4. Build the schedule around dependencies
Replace generic lead times with confirmed dates and prerequisites. A connection order, a reachable building manager and an approved loading slot are separate matters. Ask providers to confirm when the new site's services will actually be available for testing.
For every phase, enter a date, time, owner and status. Keep an estimated date marked as unconfirmed. Allow time between setup and the team's start for testing and repairs; the amount depends on your systems and operation.
| Phase | Requirement before proceeding | What to record |
|---|---|---|
| Prepare the new premises | Use, access and furniture positions agreed | Room release, keys and contacts |
| Check services and a test workstation | Required utilities and communications actually usable | Test result and unresolved dependencies |
| Finalise inventory and scope | Quantities, routes, destination zones and tasks confirmed | Dated inventory and booking version |
| Switch over the old operation | Internal approval and agreed IT preparation complete | Shutdown sequence, backup status and fallback |
| Transport and assemble | Destination zones accessible and responsible people present | Handovers, discrepancies and assembly condition |
| Test and bring the team back | Essential workflows tested or an explicitly approved temporary arrangement active | Acceptance, outstanding items and team update |
5. Describe the moving service precisely
Inventory the office room by room: furniture, monitors, devices, cartons and special items. For both addresses, describe floors, lift dimensions, narrow points, carrying distances and agreed loading times. Heavy or delicate equipment needs enough information, and sometimes a survey, before a provider can confirm the job.
Assign packing, furniture dismantling, carrying, transport, assembly and packaging collection individually. Device shutdown, backups, network changes and functional tests need their own owner and scope. Compare quotes against the same dated inventory and plan.
Quote photos should show only the necessary furniture and access details. Customer records, screen contents, access codes and unnecessary personal data do not belong in an enquiry. Agree a suitable transfer method and a named recipient.
- Identify the workstations that should be dismantled last and set up first.
- Agree packaging and permitted handling for delicate equipment with IT and the moving partner.
- Confirm who may receive handovers at the old and new sites.
- Send dated written updates when inventory, access or timing changes, and obtain confirmation.
6. Make a proceed-or-postpone decision before shutdown
A temporary workstation or mobile connection becomes a useful reserve only once access, capacity and internal approval for the intended tasks have been established and tested.
Set a decision point before dismantling the old operation. The authorised person should review outstanding prerequisites with IT, departments and the moving partner. If an essential condition is missing, make a deliberate choice: postpone the affected step or activate the fallback already checked.
IT should confirm a suitable current backup, a tested recovery method and responsibility for incidents. The existence of a backup file does not establish that recovery will work. For personal data, Article 32 GDPR requires safeguards appropriate to risk, including availability, recoverability and regular assessment.
- Are the first rooms needed accessible and released for their planned use?
- Have connections and access been tested, or is an internally approved alternative working?
- Has the responsible IT team confirmed backup, shutdown order and recovery?
- Can the required providers and internal decision-makers be reached during the agreed window?
- Does the team know the current status, when the next update will arrive and where to report faults?
7. Accept the new site by testing real workflows
Check at least one representative workstation for each required workflow, plus the particular requirements of the other affected workstations. Use approved test data. A successful network connection alone does not show whether the business application, telephone service or enquiry handling works.
Add a name, time, result, fault owner and retest to this table. Essential faults prevent approval of the affected workflow unless a temporary arrangement has been explicitly accepted. Minor remaining jobs can have a named owner and deadline.
| Check | Observable result | Who confirms? |
|---|---|---|
| Workstation and routes | Stable furniture, usable workspace, safe cables and walking routes | Internal owner of workplace setup and safety |
| Login and data access | Authorised user can reach the required approved data and applications | IT with the relevant department |
| Telephone and email | Incoming and outgoing test contacts reach the correct destination | Communications owner |
| Essential business workflow | Approved test transaction can be completed to the required outcome | Owner of that workflow |
| Required additional equipment | Printing, scanning or another necessary function tested successfully | Relevant department with IT |
| Fault reporting and fallback | Team knows the contact; the planned reserve is usable | Move lead and relevant task owners |
8. Close outstanding items and enquire about a moving partner
Keep handover records, inventory reconciliation, discrepancies and test results together. Close each outstanding item only after checking it. Return old premises and keys through the agreed handover process; the last carton leaving the building is not the only condition to consider.
Umzughilfen is a marketing and referral service based in Idstein for moving enquiries in the Rhine-Main area. For an office move, describe inventory, access, requested work and business time windows. The selected independent partner confirms availability, dates and the exact service scope.
The quote, moving contract, work, invoice and payment are handled directly with the company named in advance. IT work is included only when expressly agreed with a suitable provider. Umzughilfen remains responsible for its own referral and data-protection duties.
Office move questions
Can an office move take place without any downtime?
That cannot be promised in general. Define essential workflows, acceptable interruptions and tested fallback arrangements. A phased move may suit the business, but it requires coordinated staffing, available connections and clear handovers.
How early should preparation begin?
As soon as the new site and affected workflows are known. The longest dependency determines the lead time, such as room availability, connection provision, specialist equipment or provider availability. Obtain specific date confirmations and allow for tests before work resumes.
Who decides whether the team can start in the new office?
The internally authorised person decides using the agreed criteria and feedback from IT and departments. The moving partner confirms the work it was commissioned to do; that does not automatically authorise business workflows to restart.
Does the moving company automatically restart the IT systems?
No. Transport, shutdown, backups, network changes and restart must be described and commissioned separately. Name the responsible IT team and agree handovers, testing and incident support before the move.
What information is needed for an office-moving enquiry?
Inventory and destination zones, both addresses, floors, lift dimensions, carrying and loading routes, requested work, time windows and priorities. Share only necessary details; sensitive file contents and access credentials do not belong in a quote enquiry.
Sources and scope
Source research dated 17 October 2026; linked primary sources are in German. The tables, sequence and checks are original editorial working aids for internal coordination. The responsible IT team makes technical decisions; the business's designated staff assess the actual workplace layout. No specific duration or uninterrupted operation is promised.